The thatching of the 3 bedroomed house is now complete and we are now waiting for the tiler to come and start tiling and putting door handles, windowpanes and do all the finishing touches.
Our next step will be furnishing the house as well as the system for the toilets.
We need 8 showers, 8 toilet seats and all the other accessories to finish the toilets and showers. Furthermore septic tanks and bringing water from the borehole.
Thank you for your ongoing support!















Published by